Lesson 09: Directing a Project Process
What can you say about the Directing a Project process? Can you explain who’s responsible for this process? What about the different decisions made in this process?
Based on AXELOS PRINCE2® material. Reproduced under licence from AXELOS. All rights reserved.
Note: PRINCE2 2017 edition is now called PRINCE2 6th edition.
- 00:10 – Directing a Project Process
- 00:12 – This is where the Project Board work
- 00:14 – Actually, it’s where the Project Board make decisions
- 00:18 – We know now that the Project Board just make decisions; well, that’s mainly what they do
- 00:23 – And this allows them to control the project
- 00:27 – We say that the Project Board direct the project while the Project Manager manages the project
- 00:34 – The purpose of the Directing a Project process is to enable the Project Board to be accountable for the project’s success by making key decisions
- 00:45 – And have overall control by delegating day-to-day management of the project to the Project Manager
- 00:53 – So the Project Manager runs the project on their behalf
- 00:58 – So let’s take a look at the objectives and decisions that the Project Board will take during the project
- 01:07 – The first objective is to ensure that there is authority to initiate the project
- 01:12 – This is also the first decision to initiate the project
- 01:15 – So it’s taken at the end of the Starting Up a Project process and allows the next process to start, which is the IP process
- 01:24 – The second objective then is to ensure authority to deliver the project’s products
- 01:30 – So this allows the project to start delivering products
- 01:34 – And this decision is taken at the end of the Initiation Stage or IP process
- 01:42 – The next decisions are all to allow each delivery stage to start
- 01:48 – So the Project Board makes a decision for each delivery stage
- 01:52 – And that gives them lots of control
- 01:55 – And also they have to spend a minimum amount of time on the project because they’re just there to make decisions
- 02:03 – Another objective is to ensure that there is authority to close the project
- 02:08 – So this is the last decision that they take and they will send out the communication and set a date to close the project budget
- 02:15 – That’s part of that decision
- 02:17 – There are other objectives as well
- 02:19 – So for example, to ensure that there was an interface between the project and the next layer, so the CPC layer
- 02:28 – Also, to ensure that the management direction and control are provided throughout the project’s life
- 02:34 – So they can give advice to the Project Board
- 02:37 – The Project Board again do this with decisions and tolerances and reports
- 02:44 – Next objective, to ensure that the project remains viable
- 02:48 – So regularly checking the Business Case, which includes the expected benefits and major risks
- 02:55 – And the last objective is to ensure that the plans for realizing the post project benefits are managed and reviewed
- 03:05 – The Project Board will check this, will be done after the project by the CPC
- 03:12 – So they will check the expected benefits because the project by then will be shut down
- 03:18 – So that was it for the objectives
- 03:21 – Also note that the Project Board don’t have to spend much time
- 03:25 – And mainly only come together to review documents and make a decision
- 03:30 – Before going any further, let me give you some context for the Directing a Project process
- 03:35 – So the trigger for the first decision is made by the Project Manager at the end of the starting of a project process
- 03:44 – When they request to initiate a project
- 03:47 – The Project Board then makes a decision while the Project Manager runs the project for them
- 03:53 – And the Project Board provides guidance where necessary
- 03:57 – The Project Board uses tolerance, reports and decisions to control the project
- 04:02 – And they communicate with the layer above, keep them informed
- 04:07 – And if they learn something that might be useful to the project, then they can pass this on to the Project Manager as well
- 04:13 – They also check the project is still viable all the way during the project
- 04:19 – Now let’s look at the activities one by one
- 04:22 – So, like before you just have to understand them
- 04:25 – And we have already covered these actually in the course so far
- 04:30 – The first activity, and first decision, is authorize initiation
- 04:35 – The trigger for this first Project Board get together is the request from the Project Manager after the starting of a project process
- 04:44 – The Project Manager will provide them with the Project Brief
- 04:48 – The Project Board will then review the Project Brief and make their big decision
- 04:53 – Then they can send out a communication to say Project X has started.
- 04:59 – And their decision is called Authority to Initiate a Project
- 05:04 – Don’t worry about remembering the exact names, just understand them
- 05:09 – And now the IP activities can begin
- 05:11 – This is also called the Initiation Stage or what I call the Planning Stage
- 05:17 – Most of the work here is about requirements and planning
- 05:21 – And this is all facilitated by the Project Manager
- 05:24 – The second decision is Authorize a Project
- 05:27 – So the second time the Project Board come together
- 05:31 – The trigger for this second decision is the request from the Project Manager and this request is called Request to Deliver a Project
- 05:40 – Again the Project Board will send out a notification to chosen stakeholders that this project is now starting the delivery stages
- 05:49 – The Project Board will also make a decision to allow the next stage to start
- 05:53 – This will be the first delivery stage, meaning that products will get created and delivered to the users
- 06:01 – So the Project Board will authorize the Stage of Exception Plan
- 06:05 – And this will allow the first delivery stage to start
- 06:10 – PRINCE2 uses the controlling stage activities to help manage each stage
- 06:16 – The Project Manager would run the controlling stage process until all the products outlined in the Stage Plan have been done
- 06:25 – At the end of the stage, they will plan the next stage and this is done in the Stage Boundary Process
- 06:31 – Then the Project Manager will request the Project Board to allow them to continue to the next stage
- 06:38 – The Project Board will normally review the performance of the last stage and then review the next stage plan
- 06:45 – And then, if they agree, they will authorize the next stage to start
- 06:50 – So this cycle will continue for each delivery stage
- 06:56 – During this stage, the Project Board can also give advice to the Project Manager
- 07:01 – And this advice is called Giving Ad Hoc Direction, that’s the PRINCE2 name
- 07:07 – For example, if the Project Manager meets a big issue, for example, if stage tolerance is exceeded
- 07:13 – The Project Manager will create a report called the Exception Report
- 07:19 – The Project Board will consider this Exception Report and they can even decide to shut down the project
- 07:26 – This is called a Premature Close
- 07:29 – Or they can ask the Project Manager to update the Stage Plan to complete the current stage
- 07:34 – And we call this the Exception Plan, so they create a new plan to complete the current stage
- 07:41 – After the Exception Plan is completed, the Project Manager will again ask the Project Board to approve because remember they are going out of tolerance
- 07:51 – The Project Board would review the Exception Plan and if they approve, then the Project Manager will use this Exception Plan to continue the current stage
- 08:01 – And they can continue the stage as normal until all the stage products have been delivered
- 08:06 – Until the rest of the stage products have been delivered
- 08:10 – So that’s an overview of how the Project Board deal with big issues
- 08:14 – And as you can see, it gives them more control over the project
- 08:20 – The Project Manager can also ask the Project Board for advice
- 08:24 – And this can be done at a meeting, via an issue report or e-mail or even telephone call
- 08:30 – The Project Board can also seek advice from the layer above, the CPC layer
- 08:36 – And if necessary, they can pass along some information to the Project Manager if they think it is going to be helpful for them to manage the project
- 08:45 – So this gives an overview on how requests for advice and exceptions are handled
- 08:52 – Next now, how the project is closed
- 08:56 – So there are two ways to close a project, so we have the normal way and the early way
- 09:02 – The early way we call it the Premature Close
- 09:05 – So the Premature is the early one and this decision is by the Project Board
- 09:10 – And the natural way is if all the work has been done as normal and all the necessary products have been delivered
- 09:17 – So both ways trigger the Closing a Project process
- 09:23 – After the Closing a Project process activities, the Project Manager then can recommend to the Project Board to close the project
- 09:32 – So the Project Manager cannot close the project, this can only be done by the Project Board
- 09:38 – The Project Manager just prepares the project for closure
- 09:42 – So this is the last decision for the Project Board in a project
- 09:46 – They check that their products have been accepted by the users and perhaps ask for proof and they should ask for proof
- 09:54 – And then they send out a closure to communication again to all the chosen stakeholders
- 10:00 – So that’s it for all the decisions for the Project Board
- 10:03 – Now let’s take a quick look at the inputs and the outputs
- 10:08 – There are inputs for each decision and outputs, which are basically all the same
- 10:14 – So for example, the inputs to authorizing each stage, we will have the End Stage Report and the Next Stage Plan
- 10:24 – The inputs for closing of a project closure are all the documents created in the Closing a Project process and the PID
- 10:32 – So basically all the information that we have in the project
- 10:35 – And the outputs are always the same, we have authorizations, notifications and approved documents
- 10:43 – So remember again that the purpose of the Directing a Project process is to enable the Project Board to be accountable for the project by making key decisions
- 10:55 – And have overall control while delegating or giving day-to-day management of the project to the Project Manager.
OK, to be sure, try to name all decisions made in this process, and the way they are connected to the other processes.
Here you can submit your questions related to the content of the course. (For other questions, use the support system). The trainer's reply will be email to you in 48 hours.
The first lessons of the course, including this one, are available for free, even without registration.
You can purchase the course to access all lessons, additional material, and coaching:
More info and purchase options